| Tuna Company set the following standard unit costs for its single product. |
| Direct materials (27 Ibs. @ $4 per Ib.) | $ | 108.00 |
| Direct labor (8 hrs. @ $8 per hr.) | 64.00 | |
| Factory overhead—variable (8 hrs. @ $5 per hr.) | 40.00 | |
| Factory overhead—fixed (8 hrs. @ $7 per hr.) | 56.00 | |
| | | |
| Total standard cost | $ | 268.00 |
| | | |
| | ||
| The predetermined overhead rate is based on a planned operating volume of 60% of the productive capacity of 40,000 units per quarter. The following flexible budget information is available. |
| Operating Levels | ||||||
| | ||||||
| 50% | 60% | 70% | ||||
| Production in units | 20,000 | 24,000 | 28,000 | |||
| Standard direct labor hours | 160,000 | 192,000 | 224,000 | |||
| Budgeted overhead | ||||||
| Fixed factory overhead | $ | 1,344,000 | $ | 1,344,000 | $ | 1,344,000 |
| Variable factory overhead | $ | 800,000 | $ | 960,000 | $ | 1,120,000 |
| | ||||||
| During the current quarter, the company operated at 70% of capacity and produced 28,000 units of product; actual direct labor totaled 222,000 hours. Units produced were assigned the following standard costs: |
| Direct materials (756,000 Ibs. @ $4 per Ib.) | $ | 3,024,000 |
| Direct labor (224,000 hrs. @ $8 per hr.) | 1,792,000 | |
| Factory overhead (224,000 hrs. @ $12 per hr.) | 2,688,000 | |
| | | |
| Total standard cost | $ | 7,504,000 |
| | | |
| | ||
| Actual costs incurred during the current quarter follow: |
| Direct materials (751,000 Ibs. @ $4.10) | $ | 3,079,100 |
| Direct labor (222,000 hrs. @ $7.75) | 1,720,500 | |
| Fixed factory overhead costs | 1,968,679 | |
| Variable factory overhead costs | 1,843,019 | |
| | | |
| Total actual costs | $ | 8,611,298 |
| | | |
| | ||
references
| 1. | Compute the direct materials cost variance, including its price and quantity variances.(Do not round your intermediate calculations. Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e., zero variance). Input all amounts as positive values. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.) |
| Direct materials cost variance | $ | |
| Price variance | $ | |
| Quantity variance | $ | |
| | ||
| Compute the direct labor variance, including its rate and efficiency variances.(Do not round your intermediate calculations. Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e., zero variance). Input all amounts as positive values. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.) |
| Direct labor cost variance | $ | |
| Rate variance | $ | |
| Efficiency variance | $ | |
| | ||
| Compute the overhead controllable and volume variances.(Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e., zero variance). Input all amounts as positive values. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.) |
| Controllable variance | $ | |
| Fixed overhead volume variance | $ | |
| | ||
Attachments:
Economic Debate- Progressive Income Tax For this Economic Debate, we are going to discuss the…
TOPIC: Going Global Discussion Thread 1 (initial post due Wednesday for full credit) Please note:…
Assignment Topic This week will culminate in the creation of a narrated PowerPoint to create…
The Assignment must be submitted on Blackboard (WORD format only) via allocated folder. Assignments submitted…
you need to post your 2-page information flier to share with your Final Project Group.…
discussion: Discuss the methods used at your company to measure and ensure quality products and…