Probability and Network Analysis

Conceptual Questions (10 points each)

Don't use plagiarized sources. Get Your Custom Essay on
Probability and Network Analysis
For $10/Page 0nly
Order Essay

C1. Explain the concept “slack” in project management? What’s the connection – and what’s the difference –between slack on a single activity and slack on a path?

C2. What assumptions are needed to calculate the probability that a project will be completed by a target date? When might these assumptions not be well satisfied?

C3. Is the critical path necessarily the path that poses the greatest risk for a project manager?

C4. Using Internet resources, identify a large firm that offers project management services. Explain briefly one of their recent project management contracts.

Quantitative Questions (20 points each)

1. The following table describes a project prior to any crashing of activities. For every week that the project duration extends beyond 25 weeks, there is a penalty of $1,000. Indirect costs on this project are $2,500 per week.

Activity Predecessor(s) NT (weeks) CT (weeks) NC ($000) CC ($000)
A None 5 3 2 4
B None 9 8 4 7
C A 10 8 10 12
D A, B 4 3 3 7
E B 3 2 4 5
F D 9 6 4 10
G E, F 2 2 2 2
H G 9 6 8 11
I C, F 9 7 7 15

(a) What path(s) is/are critical, prior to any crashing of activities?

(b) What is the duration of the project prior to any crashing of activities?

(c) After appropriate crashing of activities, what is the duration of the minimum cost project? (d) What path(s) is/are critical in the minimum cost project?

(e) How much cheaper is the minimum cost project, compared to the project before crashing?

2. The following table describes a project.

Activity Predecessor(s) Time (days)
A None 7
B None 5
C B 3
D A 2
E A, B 5
F D, E 9
G C, E 3

Page 1 of 2

POM 610 632, Fall 2019. Assignment #2.

(a) You need to ensure that the project is completed as soon as possible. The activities cannot however be crashed. You have one other option: you could reassign one employee, who is currently scheduled to work on Activity G, to help the employee scheduled to work on Activity F. Each day that you reassign the employee will entail that Activity G increases its time by one day, but and Activity F reduces its time by one day. How many days should you reassign the employee?

(b) Draw a Gantt chart for this project, using EF-EF for the critical activities, the ES-EF time for noncritical activities, and the slack time for non-critical activities.

3. The following table describes a project.

Activity Predecessor(s) a (days) m (days) b (days)
A None 20 30 40
B A 80 84 100
C A 46 60 98
D C 30 50 76
E B 25 30 41
F D, E 25 30 35
G F 10 20 30
H G 20 25 60
I G 8 10 12
J H, I 20 25 60

(a) What path(s) is/are critical? What is the expected project duration?

(b) Considering the critical path, what is the probability of completing the project in 265 days?

(c) For the second-longest path, what is the probability of completion in 265 days?

(d) If the project manager wants to set a project deadline such that there is 90% chance of completing the project by the deadline, how many days is the deadline?

Page 2 of 2

admin

Recent Posts

Economic Debate #3- Progressive Income Tax – The Homework Helper

Economic Debate- Progressive Income Tax For this Economic Debate, we are going to discuss the…

2 years ago

MKT 6120 – Marketing Management – Davis Learning Engagement #7

TOPIC: Going Global Discussion Thread 1 (initial post due Wednesday for full credit) Please note:…

4 years ago

jvjvjhvjhvhjvj

Assignment Topic This week will culminate in the creation of a narrated PowerPoint to create…

4 years ago

Students are supposed to select a technological organization of their choice.

The Assignment must be submitted on Blackboard (WORD format only) via allocated folder. Assignments submitted…

4 years ago

Increases the risk of wildfires

you need to post your 2-page information flier to share with your Final Project Group.…

4 years ago

Statistics for Technology management

discussion: Discuss the methods used at your company to measure and ensure quality products and…

4 years ago