Cost estimation, cumulative average time learning curve The Nautilus Company, which is under contract to the U.S. Navy, assembles troop deployment boats. As part of its research program, it completes the assembly of the first of a new model (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that Nautilus submit a proposal on the cost of producing another six PT109s. Nautilus reports the following cost information for the first PT109 assembled and uses a 90% cumulative average time learning model as a basis for forecasting direct manufacturing labor hours for the next six PT109s. (A 90% learning curve means b = –0.152004.)
Required
1. Calculate predicted total costs of producing the six PT109s for the Navy. (Nautilus will keep the first deployment boat assembled, costed at $1,575,000, as a demonstration model for potential customers.)
2. What is the dollar amount of the difference between (a) the predicted total costs for producing the six PT109s in requirement 1, and (b) the predicted total costs for producing the six PT109s, assuming that there is no learning curve for direct manufacturing labor? That is, for (b) assume a linear function for units produced and direct manufacturinglabor hours.
Economic Debate- Progressive Income Tax For this Economic Debate, we are going to discuss the…
TOPIC: Going Global Discussion Thread 1 (initial post due Wednesday for full credit) Please note:…
Assignment Topic This week will culminate in the creation of a narrated PowerPoint to create…
The Assignment must be submitted on Blackboard (WORD format only) via allocated folder. Assignments submitted…
you need to post your 2-page information flier to share with your Final Project Group.…
discussion: Discuss the methods used at your company to measure and ensure quality products and…