Given the following information, answer the questions about this project:
Activity
Expected Duration
Predecessors
A
4 days

B
9 days
A
C
11 days
A
D
5 days
B
E
3 days
B
F
7 days
C
G
3 days
D, F
H
2 days
E, G
I
1 day
H
1. Draw the network as a Gantt chart.
2. What is the critical path? Which activities have slack time?
3. What would happen if activities B and D each took 5 extra days to complete instead of the
expected duration? How would the critical path change?

Purchase answer to see full
attachment

Don't use plagiarized sources. Get Your Custom Essay on
BADM 635 University of The Cumberlands Lagging Crashing & Activity Networks HW Project Scheduling: Lagging, Crashing, and Activity Networks.Attach word fil
For $10/Page 0nly
Order Essay
Calculator

Calculate the price of your paper

Total price:$26

Need a better grade?
We've got you covered.

Order your paper